Important Notice of Water Pipeline Replacement

Homes located on Telluride Court, Westside Street, Telluride Street, Westside Circle and Telluride Place in Roxborough Village

 

Schedule and Updates

Construction Schedule – Click on the link to see the schedule (updated September 6, 2018)
We are slightly behind schedule but should have the project completed mid to late September.

The contractor for this project, Redline Pipeline, LLC, mobilized on May 7 and is anticipated to complete the project by mid-September.  The sequence of construction currently is Segment 4 and Segment 1 concurrently, then Segments 2, then 5, then 3.

 

Click here to review the PowerPoint presentation about the Water Pipeline Replacement.

 

 

Why is the District replacing water lines?
[su_expand more_text=”Click to Expand” less_text=”Show less” height=”0″ hide_less=”no” text_color=”#333333″ link_color=”#8B0e04″ link_style=”default” link_align=”left”]Over the last 10 years, there have been over 13 waterline breaks in the Roxborough Village on Telluride Court, Westside Street, Telluride Street, Westside Circle and Telluride Place. These waterline breaks have occurred, at all times of day, due to the high corrosive nature of soil in the area. Breaks in a pipeline can also cause water quality issues such as brown water to occur.[/su_expand]

Why can’t the District just wait until the pipelines break?
[su_expand more_text=”Click to Expand” less_text=”Show less” height=”0″ hide_less=”no” text_color=”#333333″ link_color=”#8B0e04″ link_style=”default” link_align=”left”]Waiting until they break means water outages happen without notice for residents in the area, pipeline breaks can happen at any time of night or on holidays, treated water is wasted, significant road damage can occur, resulting in expensive emergency repairs. That’s why the District has budgeted for 3,000 feet of the most corroded water pipes to be replaced in 2018.[/su_expand]

If I live on Telluride Court, Westside Street, Telluride Street or Westside Circle, will my water be shut off?
[su_expand more_text=”Click to Expand” less_text=”Show less” height=”0″ hide_less=”no” text_color=”#333333″ link_color=”#8B0e04″ link_style=”default” link_align=”left”]For homes located on these streets, there will be a short interruption (approximately 30 minutes) while the temporary water system is connected to each house. After the main water can be reinstated, there will be another short interruption (approximately 30 minutes) to disconnect the temporary water system.[/su_expand]

How long will the project take?
[su_expand more_text=”Click to Expand” less_text=”Show less” height=”0″ hide_less=”no” text_color=”#333333″ link_color=”#8B0e04″ link_style=”default” link_align=”left”]The construction is expected to last from mid-April to mid-September, during which time temporary water pipes (see PowerPoint for visuals) will be installed at each home in the area.[/su_expand]

Will this project affect my sewage (wastewater) pipelines?
[su_expand more_text=”Click to Expand” less_text=”Show less” height=”0″ hide_less=”no” text_color=”#333333″ link_color=”#8B0e04″ link_style=”default” link_align=”left”]No, this project is only for water pipeline replacements and thus will not affect the removal of sewage from your home.[/su_expand]

How will the project prevent corrosion of the replacement pipelines?
[su_expand more_text=”Click to Expand” less_text=”Show less” height=”0″ hide_less=”no” text_color=”#333333″ link_color=”#8B0e04″ link_style=”default” link_align=”left”]The District will combat corrosion in a couple ways: Sacrificial anodes attached to pipe so anodes decay prior to pipe. This system is typically designed for a 50 to 100 year anode decay life; and by installing of PVC pipe.[/su_expand]

How will we be notified?
[su_expand more_text=”Click to Expand” less_text=”Show less” height=”0″ hide_less=”no” text_color=”#333333″ link_color=”#8B0e04″ link_style=”default” link_align=”left”]For homes located in the area where the pipeline replacements will be occurring there will be a posted 48-hour notice. A District or contractor representative will also be going door-to-door approximately 30 minutes to an hour prior to the water shutoff. Updates will also be posted to this website.[/su_expand]

Will the construction be disruptive?
[su_expand more_text=”Click to Expand” less_text=”Show less” height=”0″ hide_less=”no” text_color=”#333333″ link_color=”#8B0e04″ link_style=”default” link_align=”left”]Yes, the construction will be very disruptive, inconvenient, loud and messy. Roads will have temporary uneven driving surfaces, windblown dust may occur, and there will be construction noises during the weekday. [/su_expand]

What about parking my car?
[su_expand more_text=”Click to Expand” less_text=”Show less” height=”0″ hide_less=”no” text_color=”#333333″ link_color=”#8B0e04″ link_style=”default” link_align=”left”]To make construction go easily and to protect the cars, street parking will be unavailable in the vicinity of where the crews are working. Any cars parked on driveways or in a garage, will not have access to the street for up to 8 hours. There will be road signs indicating where parking on the streets is prohibited.[/su_expand]

What are the construction hours?
[su_expand more_text=”Click to Expand” less_text=”Show less” height=”0″ hide_less=”no” text_color=”#333333″ link_color=”#8B0e04″ link_style=”default” link_align=”left”]The hours will be from 8am until 5pm. During nights and weekend, segments of the roads will be closed to through traffics and open only to traffic of residents in the area. There will be no flaggers or lights to direct traffic on nights and weekends.[/su_expand]

What can I do to help?
[su_expand more_text=”Click to Expand” less_text=”Show less” height=”0″ hide_less=”no” text_color=”#333333″ link_color=”#8B0e04″ link_style=”default” link_align=”left”]If possible, use alternate routes away from the crews. Do not park on the street in the vicinity of the crews. Plan ahead for your water needs, access and any deliveries. Watch for potential problems and if you see something of question, contact us immediately, no matter what time of day by calling: 303-979-7286 during normal business hours (8am to 4:30pm) and after hours calling: 303-281-9338.[/su_expand]

Is it possible the construction schedule can be delayed?
[su_expand more_text=”Click to Expand” less_text=”Show less” height=”0″ hide_less=”no” text_color=”#333333″ link_color=”#8B0e04″ link_style=”default” link_align=”left”]Yes there may be construction schedule delays due to the weather or other reasons outside of our control. [/su_expand]

When will the roadway repaving occur after the construction is done?